PROJECT  SUMMARY:
With the help of a grant from the State of Michigan, the university reconfigured Oliver Street, the campus road that runs between Stadium and Oakland Drives.

The project took place in three stages over the summer of 2008 and was completed in August, in time for the start of fall semester.  The office "road opening' was Friday, August 29, 2008.

The total scope of the project included a new roadway and sidewalks, bicycle paths, and reconstructed parking lots.

Also included in the project was a stormwater management plan to prevent building and parking lot run-off from entering the Arcadia Creek watershed.

Existing roads configuration and construction sequence.
Click to enlarge.
Construction Stages
 
Map of future campus roads after construction is complete. Click to enlarge
Reconfiguration Plan

 

Construction photos
Construction Photos:
May 2008
July 2008
August 2008

 

 

Planning Division of Facilities Management; Mail #5313
Western Michigan University
1903 W. Michigan Ave.
Kalamazoo MI 49008 USA
(269) 387-8543 or 387-8544 | (269) 387-8818 Fax
campus-facility@wmich.edu

 

Shipping Address:
Planning Division; Facilities Management
Campus Services Building

1201 Oliver Street

Kalamazoo, MI  49008